Maint Plans

Logistics : PM and its sub-modules & SM

Moderators: Snowy, thx4allthefish, PJA

Post Reply
Ralph
Posts: 56
Joined: Mon May 19, 2003 3:57 pm
Location: USA- Virginia

Maint Plans

Post by Ralph » Fri Jul 17, 2009 1:37 pm

Need some help ....I have a monthly compliance inspection and here what I'd like the system to do, but not sure if I can:
Monthly/Single Cycle Plan
1) Generate the Order on the 1st day of the month (Key Date) with the Order Basic Start date being the 1st and the Basic Finish Date being the end of the month (30days later). The actual task takes approximately 5hrs, so that's what the Task list says, but we have 30 days to complete the task.
Can I do this or does everything have to be manipulation through the Task list/Scheduling Type. Currently my Scheduling Type (Adjust dates) is set to 2.

Thanks for any help. (ver ECC6.0)

Bothy
Posts: 65
Joined: Sun Oct 27, 2002 12:23 pm
Location: Scotland

Re: Maint Plans

Post by Bothy » Mon Jul 20, 2009 9:47 am

Hi Ralph,

We get the result you are loking for by manipulating the dates in the strategy packages. If you set the monthly package Initial = 0 Subsequent =30 that should get the dates as you expect. BSD = 1st BFD = 30 days later.
With regards to Scheduling: ours is set to 4 "Do not adjust basic dates etc."

Hope this is some help.

Bothy