CAT2 / CATA

Logistics : PS

Moderators: Snowy, thx4allthefish

Post Reply
rishikesh

CAT2 / CATA

Post by rishikesh » Sun Jan 19, 2003 10:18 am

While posting time on an internal activity, it asks for the work center (if you had not filled in while activity creation). However when you post time to this activity under an employee number (do also the cats transfer) then it is posting the cost on the cost center assigned to the work center to which the employee is assigned to.

Will this posting reduce the capacity requirement of the original work center assigned to the activity?

What is the mechanism of the posting actuals via CAT2/CATA in relation to the work centers (assigned originally to the activity & the one where the actual work was done, & the cost centers).

fatman
Posts: 126
Joined: Thu Dec 12, 2002 1:23 am
Location: San Francisco

CATS

Post by fatman » Tue Jan 28, 2003 11:03 pm

Hi rishi,

Based on the planned man hours in the activity , work center capacity is calculated .

When you post the actual manhours from CATS to PS, system creates a confirmation in PS. This will not affect your planned capacity or manhours.


FATMAN