Change data in copy network from ...

Post by Guest » Mon Mar 03, 2003 5:08 am

Hi Sapfans

Is posible to change any data when copy a network? For example, we need put blank in the info record and PS01 in control key when copy a network in the project builder. Using any user exit?

Thank in advance,

fatman
Posts: 126
Joined: Thu Dec 12, 2002 1:23 am
Location: San Francisco

network

Post by fatman » Tue Mar 18, 2003 11:01 pm

Hi ,

Why do you want to complicate things?

Create a new standard network with blank in the info record and PS01 in the control key and copy the network in the project builder.

FATMAN