Is it possible to fix the components of a planned order after changing them, yet still have MRP update planned order quantities if the demand changes?

In the header, under firming, we cannot uncheck the Plnd Order indicator while the Component indicator is checked. Is there any workaround for that?
MMPP
 
Posts: 392
Joined: Tue May 27, 2003 9:42 am
Location: My Desk

Re: Firmed Planned Orders

Postby Ramarao » Thu Aug 10, 2017 4:32 pm

What is firming for if you still want to allow MRP to update quantity? You must not change the date, is it?
- Ramarao
Ramarao
 
Posts: 717
Joined: Wed Dec 11, 2002 7:16 pm
Location: Dallas, TX

Re: Firmed Planned Orders

Postby MMPP » Thu Aug 10, 2017 5:39 pm

Thanks for the response!

We are updating components in planned orders due to substitutions, where we are not getting the component planned according to the BOM.

So we want to keep the updated components, but quantities would need to be adjusted in case our PIRs change.
MMPP
 
Posts: 392
Joined: Tue May 27, 2003 9:42 am
Location: My Desk


Return to Logistics PP

Who is online

Users browsing this forum: No registered users and 7 guests





This website is not affiliated with, sponsored by, or approved by SAP AG.